SCHEDULE

Over 16 miles of I-80 from Minooka to New Lenox will be reconstructed, including over 30 bridges. Construction will be implemented in phases to minimize impacts on traffic. 

​

The I-80 reconstruction project will occur in stages, a few miles at a time. Completion of one phase is required to advance to the next, with full reconstruction anticipated to be completed in 2028. 

​

While the project is currently in various stages with ongoing community coordination, sections of the interstate are moving forward with construction.

COMPLETED

 

A. HOUBOLT ROAD EXTENSION

A joint project with Joliet, Will County, and CenterPoint Properties.

​

B. U.S. 30 INTERCHANGE IMPROVEMENTS

This includes I-80 reconstruction and added lanes between U.S. 30 and Gougar Road)
 

PHASE ONE (CURRENTLY UNDERWAY)

 

C. HOUBOLT ROAD DIVERGING DIAMOND INTERCHANGE CONVERSION

Projected Time Frame: 2023 Completion

​

D. BRIDGES AT HICKORY CREEK, RICHARDS STREET, ROWELL AVENUE/CANADIAN NATIONAL RAILROAD

Projected Time Frame: 2024 Completion

​

E. I-80: RIDGE ROAD TO RIVER ROAD RECONSTRUCTION

Projected Time Frame: 2025 Completion

​

F. SHEPLEY ROAD OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2023 Completion

​

G. WHEELER AVENUE OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2023 Completion

​

H. BRIGGS STREET OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2024 Completion

PHASE TWO (2024-2026)

 

I. RIVER ROAD OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2024

​

J. I-80: RIVER ROAD TO WHEELER AVENUE RECONSTRUCTION

This includes I-55 and Larkin Avenue Interchange reconstruction.

Projected Time Frame: 2024-2026

​

K. I-80: ROWELL AVENUE TO GOUGAR ROAD RECONSTRUCTION

This includes Briggs Street Interchange reconstruction.

Projected Time Frame: 2024-2025

PHASE THREE (2026-2028)

 

L. I-80: DES PLAINES RIVER BRIDGE REPLACEMENT

This includes Center Street and Chicago Street Interchange reconstruction. Phase Three construction is dependent on completion of land acquisition activities.

Projected Time Frame: 2026-2028

Note: Substantial completion with all lanes open on I-80 is planned for November 2028. Construction activities such as the demolition of the existing Des Plaines River bridges will continue into 2029.