SCHEDULE

Over 16 miles of I-80 from Minooka to New Lenox will be reconstructed, including over 30 bridges. Construction will be implemented in phases to minimize impacts on traffic. 

Construction is underway and anticipated to be substantially completed in 2028.

COMPLETED

 

A. HOUBOLT ROAD EXTENSION

A joint project with Joliet, Will County, and CenterPoint Properties.

B. U.S. 30 INTERCHANGE IMPROVEMENTS

This includes I-80 reconstruction and added lanes between U.S. 30 and Gougar Road)

 

C. HOUBOLT ROAD DIVERGING DIAMOND INTERCHANGE CONVERSION

PHASE ONE (CURRENTLY UNDERWAY)

D. BRIDGES AT HICKORY CREEK, RICHARDS STREET, ROWELL AVENUE/CANADIAN NATIONAL RAILROAD

Projected Time Frame: 2024 Completion

E. I-80: RIDGE ROAD TO RIVER ROAD RECONSTRUCTION

Projected Time Frame: 2025 Completion

F. SHEPLEY ROAD OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2023 Completion

G. WHEELER AVENUE OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2023 Completion

H. BRIGGS STREET OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2024 Completion

PHASE TWO (2024-2026)

 

I. RIVER ROAD OVER I-80 BRIDGE REPLACEMENT

Projected Time Frame: 2024

J. I-80: RIVER ROAD TO WHEELER AVENUE RECONSTRUCTION

This includes I-55 and Larkin Avenue Interchange reconstruction.

Projected Time Frame: 2024-2026

K. I-80: ROWELL AVENUE TO GOUGAR ROAD RECONSTRUCTION

This includes Briggs Street Interchange reconstruction.

Projected Time Frame: 2024-2025

PHASE THREE (2026-2028)

 

L. I-80: DES PLAINES RIVER BRIDGE REPLACEMENT

This includes Center Street and Chicago Street Interchange reconstruction. Phase Three construction is dependent on completion of land acquisition activities.

Projected Time Frame: 2026-2028

Note: Substantial completion with all lanes open on I-80 is planned for November 2028. Construction activities such as the demolition of the existing Des Plaines River bridges will continue into 2029.