SCHEDULE

Over 16 miles of I-80 from Minooka to New Lenox will be reconstructed, including over 30 bridges. Construction will be implemented in phases to minimize impacts on traffic. 

​

Construction is underway and anticipated to be substantially completed in 2028.

COMPLETED

 

A. HOUBOLT ROAD EXTENSION

A joint project with Joliet, Will County, and CenterPoint Properties

​

B. U.S. 30 INTERCHANGE IMPROVEMENTS

This includes I-80 reconstruction and added lanes between U.S. 30 and Gougar Road

 

C. HOUBOLT ROAD DIVERGING DIAMOND INTERCHANGE CONVERSION

​

D. BRIDGES AT HICKORY CREEK, RICHARDS STREET, ROWELL AVENUE/CANADIAN NATIONAL RAILROAD

​

E. I-80: RIDGE ROAD TO RIVER ROAD RECONSTRUCTION

​

F. SHEPLEY ROAD OVER I-80 BRIDGE REPLACEMENT

​

G. WHEELER AVENUE OVER I-80 BRIDGE REPLACEMENT

​

H. BRIGGS STREET OVER I-80 BRIDGE REPLACEMENT

​

I. RIVER ROAD OVER I-80 BRIDGE REPLACEMENT

​

L. RICHARDS STREET RECONSTRUCTION​

UNDER CONSTRUCTION

​

​​J. I-80: RIVER ROAD TO WHEELER AVENUE RECONSTRUCTION

Projected Time Frame: 2026 Completion

​

K. I-80: ROWELL AVENUE TO GOUGAR ROAD RECONSTRUCTION

Projected Time Frame: 2026 Completion​​

​

N. I-55 INTERCHANGE

Projected Time Frame: 2026 Completion

​

O. LARKIN INTERCHANGE

Projected Time Frame: 2026 Completion

​

P. CENTER STREET INTERCHANGE

Projected Time Frame: Winter 2025 – Fall 2027

2026-2028 CONSTRUCTION

​

Q. CHICAGO STREET INTERCHANGE

Projected Time Frame: Spring 2026 – Fall 2027

​

M. I-80: DES PLAINES RIVER BRIDGE REPLACEMENT

Projected Time Frame: 2026-2028

Note: Substantial completion with all lanes open on I-80 is planned for November 2028. Construction activities such as the demolition of the existing Des Plaines River bridges will continue into 2029.

I-80MapandFactSheet_RevisedLegend_020426.jpg